  1. Hydraulic test (overpressure test) to check the tightness of pressure parts.
  2. Auxiliary machine test and verification of each electric door and damper.
  3. Oven. Remove the moisture from the furnace wall and the water in the boiler tube.
  4. The stove and pickling. Use lye and acid to remove deposits such as grease, rust, scale and other corrosion products and scales in the heating surface of the evaporation system.
  5. Furnace aerodynamic field test.
  6. Flushing. The boiler self-generated steam is used to flush out the residual slag in the primary and secondary steam pipes.
  7. Verify the security door and so on.